| Hoist assembly and testing at APPI |
Fedrick arrived at Umm Qasr in January of 2004 and took charge of the rebuilding effort of that facility as contracted to Weston. Within three months, using local contractors and laborers, he had built two barracks, a dining hall, a classroom and a warehouse. Based on that success, Fedrick was given the opportunity to bid on removing and rebuilding a boat lift destroyed during the invasion of Iraq in March of 2003. Having the lift operational was identified by the Iraqi Ministry of Defense and the Coalition Provisional Authority as being crucial to ensuring the five patrol boats in the ICDF were properly maintained and able to fulfill their mission to counter terrorism, smuggling and piracy.
Although Fedrick was a naval architect, he knew that once the 250 tons of twisted steel remaining in the water from the old lift platform were removed, getting a system in placed that would meet his 1,000 ton capacity requirement was going to be more challenging than erecting buildings. In addition to the salt water atmosphere, sand and extreme heat that went with the location, the system he was responsible for specifying needed to be safe and reliable for the ICDF crews who would be operating it long-term.
| The assembled platform |
In order to use as much of the existing lift structure as possible, Fedrick specified 10 hoists with a total capacity of 1,000 tons. Fedrick also added the caveat that after traveling 32 feet vertically, the platform could be no more than 1/16th of an inch out of plane over its 265 foot length.
| Testing the hoist system |
When Weston was awarded the contract to rebuild the ship lift, a purchase order contract was issued to APPI for the hoist system. In December of 2005, Fedrick and Champak Sadhu, Weston's lead mechanical engineer, made a trip to Beaverton where APPI had laid out the entire system for familiarization and run testing. After acceptance, the entire system was loaded into three containers and sent by sea to Umm Qasr.
Since the day the contract had been awarded to rebuild the ship lift, Fedrick and his crews had been working to remove and rebuild the old platform sitting in the water between the two wings of the ship lift dock. At the same time, they were also designing and building the 10 lift towers and hoist mounting pads in anticipation of the arrival of the containers from APPI. Without the benefit of any form of fabrication facility, the work was completed entirely on site just before the hoisting equipment arrived.
After bolting down 10 hoists, hanging 10 pairs of load blocks and reeving 10 lengths of wire rope, the controls were connected and system testing began. Over a period of a month, the platform was tested for both gross and off-center loading. Fedrick said that “Once we had everything dialed in, it made no difference to the hoists what the load was or where it was positioned – it lifted perfectly level under all conditions. There's no question APPI was the right choice for this job as their system just flat worked right.”
| Rick Fedrick shows a big smile after successful operation |
For more information on synchronized lifting, marine, and shipyards applications, visit our website: www.AlliedPower.com